Newly Found Fukushima Plant High Contamination Level May Delay Decommission
Japanese nuclear regulator adopted a draft investigation report into the 2011 Fukushima nuclear meltdown on 27 January. It says it has detected dangerously high levels of radioactive contamination at two of the three reactors, adding to concerns about decommissioning challenges.
The interim report said data collected by investigators showed that the sealing plugs sitting atop the No. 2 and 3 reactor containment vessels were as fatally contaminated as nuclear fuel debris that had melted and fell to the bottom of the reactors following the March 2011 tsunami and earthquake.
The experts measured radiation levels at multiple locations inside the three reactor buildings, and examined how radioactive materials moved and safety equipment functioned during the accident. They also said venting attempt at Unit 2 to prevent reactor damage never worked, and that safety measures and equipment designs still need to be examined.
Nuclear Regulation Commission Chairman Toyoshi Fuketa called the findings “extremely serious” and said they would make melted fuel removal “more difficult.” He said figuring out how to remove the lids would be a major challenge.

The 2019 photo of melted fuel inside of the primary containment vessel of Unit 2 reactor at the Fukushima Dai-ichi plant , зроблене 2019 року. Image: Tokyo Electric Power Co.
Removing an estimated 900 tons of melted fuel debris from three reactors is a daunting task expected to take decades, and officials have not been able to describe exactly when or how it may end.
The Fukushima plant was to start removing melted fuel debris from Unit 2, the first of three reactors, later this year ahead of the 10th anniversary of the accident. But in December, plant operator Tokyo Electric Power Co. and the government announced a delay until 2022. They said the development of a robotic arm for the debris removal – a joint project with Britain – has been delayed due to the pandemic.
Under the current plan, a remote-controlled robotic arm will be inserted from the side of the reactor to reach the molten fuel mixed with melted parts and concrete floor of the reactor. Eventually the lids also would have to be removed, but their contamination is a major setback.